The project envisages the reconstruction of the Luzhniki Olympic complex to turn it into a modern sports&entertainment center for the Moscow citizens’ leisure and recreation.
2014 – 2017
The Luzhniki Stadium reconstruction is complete; the Stadium successfully hosted FIFA World Cup 2018, it hosts world-class sporting events.
The project involves the relocation of the existing press-welding production of a leading Russian car body parts manufacturer producing more than 6.5 million parts per year. The construction project envisages the erection of a plant with an area of more than 40,000 sq. m in the Biryulyovo industrial zone.
RUR 1.2 bn (private investments)
2018–2028
As part of the St. Petersburg International Economic Forum - 2019, a 10-year SIC was concluded with OOO Alpha Automotive Technologies. The construction is underway.
The project envisages the creation of a food industry enterprise in Moscow (healthy lifestyle food products: sugar substitute, fruit and nut bars, chicory, granola, protein cereals and special food products under TM Bionova, Ol’Lait, Novasweet and Chirkoff). The space of the company production facilities will be about 10,000 sq. m. It is planned to create 233 new jobs.
RUR 633.6 m
2019–2028
As part of the St. Petersburg International Economic Forum - 2019, a 10-year SIC was concluded with OOO NovaProduct AG.
As part of the project of the Scientific Research Institute of Technical Physics and Automation (the party involved is the Nizhnie Kotly Industrial Park Management Company), it is planned to create the first industrial park in Moscow called Nizhnie Kotly.In the park, an innovative production will be launched, and research in the field of natural and technical sciences will be carried out, including nuclear medicine and radiation technology. In addition, technical control, testing and the other activities related to the testing, navigation and measuring instrument production will be carried out. The products list will include import-substituting medical equipment. It is planned to create 500 highly paid jobs.
RUR 2.1 bn
2018–2028
A SIC with the Scientific Research Institute of Technical Physics and Automation for 10 years has been concluded. Currently, the company is reconstructing the production and laboratory buildings.
The project involves the construction of an industrial complex for meat production. The total industrial complex area will be 28,000 sq. m. About 450 new jobs will be created.
RUR 1.2 bn
2019–2028
A SIC with OOO PK Elitgrupp Invest has been concluded. The company is currently creating engineering infrastructure.
The project involves the construction of a 10,000-sqare-meter technopark complex, including a production unit with a research center and administrative premises for staff. The technopark residents and leaseholders will be the companies working in the field of CVD diamond synthesis and industrial application, manufacturing the final products with a high CVD diamond conversion depth, and developing and producing modern semiconductor hardware and lasers.
Own funds (up to RUR 800 m) and borrowed funds (RUR 2 bn).
2018–2021
Potential technopark residents have been identified. The Project Documentation has been developed. The negotiations regarding the land transfer for the construction of the industrial park facilities are underway.
The project envisages to expand the ITELMA technopark territory by 0.4 hectares and, in addition to the laboratory&sports and innovative&industrial complexes available in the technopark, construct an engineering&laboratory complex, as well as a transformer substation (to be included in the ITELMA technopark).
RUR 500 m
2018–2019
A project for the engineering&laboratory complex construction has been developed. The negotiations regarding the land transfer for construction purposes are underway.
The project involves the reconstruction and significant expansion of the existing VDNKh EXPO area for congress, exhibition and concert events. The project will include a concert and congress complex with a capacity of 4 thousand people and exhibition pavilions with a total exposition area of 63 thousand sq. m.
The cost of the PPP contracts concluded in 2013-2018 is over RUR 27 bn.
2017–2021
The construction tender was won by the Tashir Group development company. The construction is underway.
The Skolkovo IC project provides the construction of infrastructure facilities for research and development, innovation activities. One of the main innovation center elements is the Skolkovo Technopark, which will occupy 60 hectares with a construction area of 145,000 sq. m. to accommodate innovative companies, laboratories and common use centers. More than 600 leading Russian and international companies will become Skolkovo Technopark residents. The Skolkovo IC will accommodate the research and development centers of such leading multinational companies as Boeing, Airbus, IBM, Intel, HP, Samsung, Cisco, Dow, GE, etc.
The cost of the PPP contracts concluded in 2013-2018 is over RUR 400 bn.
Not limited.
By now, more than 23 thousand square meters of the Skolkovo IC Technopark have already been put into operation and made available for the residents. In addition, the main center facilities include the Hypercube, the Skoltech University (Skolkovo Institute of Science and Technology), the Matryoshka cultural and business center and the building of the Research and Development Center Renova Lab. Also, there is a plan for the construction of residential quarters, i.e. the apartments for the Skolkovo Information Center residents.Ca. 2000 companies from all over Russia are taking part in the project for the Skolkovo Information Center creation.
The companies willing to participate in the project can apply for the preliminary examination online at the official project website. Also, the online applications for accommodation in the Skolkovo Technopark can be submitted at the Moscow Investment Portal.
The project involves the expansion of the existing technopark property.
RUR 606 m
2019–2022
A SIC on the investment priority project implementation agreement has been concluded. The investor is the Strogino Technopark public enterprise. At present, the company is preparing pre-project and project documentation.
The project involves the technopark construction.
5.6 billion rubles
2019–2022
An agreement on the investment priority project implementation has been concluded. The investor is AO Technopolis Moscow. At present, the company is preparing pre-project and project documentation.
The project involves the technopark construction.
RUR 2.9 bn
2019–2022
An agreement on the investment priority project implementation has been concluded. The investor is OAO Kalibr. At present, the company is preparing pre-project and project documentation.
The project involves the construction of a 2,300-meter two-station cable way with the travel time of about 7 minutes, against 30 minutes by metro, and 25 minutes by land passenger transport. The facility payback and maintenance needs are planned to be covered by direct ticket revenues, advertising and commercial space use. The facility will be the city property, while the investor will perform the construction and operate the facility for 20 years. The contract is based on a private initiative.
over RUR 3 bn
2019-2041 years (including a capital investment stage from 2019 to 2021).
At the end of 2019, it is planned to conclude a concession agreement with the winner of an open tender.
The project involves the metro rolling stock purchase, followed by the new cars maintenance throughout the entire operation period under a life cycle contract (LCC).A new approach to the metro cars purchase and repair will reduce the annual load on the city budget, provide a new generation of metro trains with an increased comfort and safety level, and get additional guarantees of the new cars reliability and schedule compliance.
RUR 352 bn
2014–2049
After the first tender in 2014–2016, 664 cars were delivered and will be maintained for 30 years. In December 2014, a contract for the supply of another 768 wagons was signed, which will be delivered in 2017–2020.Under the second contract, the manufacturer shall, by January 1, 2018, establish in Russia the local railcar production to cover at least 70%.In addition, to date, another contract has been concluded for the purchase and maintenance of 144 cars. Until 2023, it is planned to purchase another 1,500 cars.
The project involves the purchase of the new-generation low-floor buses with improved performance characteristics to be operated in Moscow. The manufacturer shall provide bus maintenance for seven years.
RUR 7.3 bn
To be defined
436 buses under the first life cycle contract (LCC) were delivered in 2016.To provide the repair and maintenance services under LCC, SUE Mosgortrans GAZ Group has created on the premises of bus fleet garage #17 the necessary infrastructure funded with investments in the amount of about RUR 55 m.
The project involves the purchase of modern electric buses and charging stations to ensure the passengers transportation in Moscow. Maintenance and repair under the contract will be carried out for 15 years.
RUR 19.3 bn
To be defined
In 2018, two life cycle contracts for the supply of 100 electric buses and 31 charging stations each were signed, which allowed to put into operation the first 30 electric buses already in September 2018. In 2019, a third contract for the supply of 100 electric buses and 36 charging stations was signed.
The electronic auctions for the supply and maintenance of 300 electric buses in total will be held until the end of 2019. In 2021, Moscow plans to stop purchasing diesel buses and switch completely to electric buses.
The project involves the purchase of the new-generation low-floor trams with improved performance characteristics to be operated in Moscow. The manufacturer shall provide tram maintenance for 30 years.
RUR 56.2 bn
To be defined
The contract concluded provides for the supply of 300 low-floor trams under LCC (100 trams per year) from 2017 to 2019.
The project envisages the modernization of the MCC railway infrastructure with an aim to arrange passenger transportation and create new stations. The city has concluded a contract with a carrier that will operate the railway using its own rolling stock, for 15 years. The further MCC infrastructure development is expected to be ensured through the construction of transfer hub (TH) facilities, including the passenger infrastructure and TH commercial facilities.
RUR 113,300 m for the MCC reconstruction,
RUR 57,000 m for the MCC transport operation set-up,
to be defined for MCC transfer hub construction.
2014–2017 - MCC reconstruction,
2016–2030 - MCC transport operation set-up,
2014–2020 – MCC transfer hub creation.
The MCC transport infrastructure construction has been completed, the MCC was opened for passengers in September 2016, with the Russian Railways (OAO RZD) as the carrier. The structuring of the commercial real estate development project as part of the MCC development is in progress. The scheme of implementation and attraction of investors has been determined. A private investor is building the Botanichesky Sad TH on the MCC that will be completed by the end of 2020.Currently, 6 TH sites (Vladykino, Novokhokhlovskaya, Delovoi Tsentr, Verkhnie Kotly, Likhobory, Zorge) are of commercial interest. The auctions to attract investors are planned to be held in 2019 and 2020.
The project provides the organization of general-practice medical clinics within a walking distance. Under the project, the city provides a preferential rental rate of “1 ruble per square meter of non-residential premises a year” for private investors, for 20 years after the investor has adapted the premises for medical purposes and has begun providing medical services, provided that the medical services are provided according to the list and the scope determined by the Moscow Department of Health.
over RUR 600 m
Not limited.
In the course of the project implementation, 66 facilities have been leased to investors. Currently, 30 facilities have been reconstructed by investors and switched to a reduced rental rate.
Under the project, the city provides a preferential rental rate of RUR 1 per 1 square meter of non-residential premises a year for 49 years to accommodate private kindergartens and schools. The investor can switch to the preferential rate after the premises have been adapted for educational activities and the services are provided in the scope determined by the Moscow Department of Education.
over RUR 1,300 bn
Not limited.
During the project, 22 real estate items were leased to investors. 18 items have already been repaired by investors and switched to a preferential rental rate.
The project provides a preferential rental rate of RUR 1 per square meter a year for cultural heritage items in exchange for investments in the restoration of those. The restoration period shall not exceed 5 years. The preferential rental period is 49 years.
over RUR 3,500 bn
Not limited.
In the course of the project implementation, 33 facilities have been leased to investors.14 cultural heritage items have already been restored, the leaseholders have switched to the rental rate of “1 ruble per square meter a year”.
The project envisages the reconstruction of the Luzhniki Olympic complex to turn it into a modern sports&entertainment center for the Moscow citizens’ leisure and recreation.
2014–2017
The Luzhniki Stadium reconstruction is complete; the Stadium successfully hosted FIFA World Cup 2018, it hosts world-class sporting events.
The project involves the Dinamo central stadium comprehensive reconstruction and adaptation to modern requirements, including the adjacent area with a 30,000 sq. m entertainment and leisure complex and 733-space underground parking lot.
2012–2018
The Dinamo stadium reconstruction has been completed, the facility has been commissioned, it hosts sporting events, ice shows, etc.
The project envisages the construction of a new, modern stadium meeting the safety requirements. The stadium capacity is 45,000 seats, the total area is 53,758 sq. m. The multifunctional complex of the Otkrytie Arena soccer stadium includes a main stadium, a sports hall with 12,000 seat stands, an administrative building and a 7,500 space parking lot.
2012–2018
It was opened on September 5, 2014 and hosted the 2018 FIFA World Cup.
The project involves the construction of a stadium with a total area of 78,000 sq. m and a capacity of 30,000 seats, as well as an adjacent hotel and administrative complex with an area of 70,000 sq. m and a multi-level 1400-space parking lot.
2007–2017
In 2016, the construction was completed. In addition to soccer matches, the stadium hosts various business, cultural and ceremonial events.
The project covers an area of about 470 hectares, incl. 333 hectare area of the Likhachov plant. The project provides reconstruction and large-scale construction. In total, more than 6 million sq. m of buildings and structures will be erected (housing, social production cluster, aboveground and underground parking lots, social facilities). More than 40 hectares will be landscaped, a 4 km long embankment and a park zone will be arranged.
The volume of investments will make about RUR 500 bn, including more than RUR 420 bn of private investments (85% of the total volume).
2014–2025
To date, the Arena Legend major hockey complex has been commissioned, the Hockey Hall of Fame, the Water Palace have been opened. In the fall of 2015, the active construction of the ZILART residential complex began.
The project involves the 101.84 hectare territory reorganization and the multifunctional comprehensive development of a total maximum area of about 1.55 million sq. m. The project implementation will result in the comprehensive improvement of the plant territory and the creation of a convenient space for the city citizens’ life and work.
RUR 140,000 m
2015–2025
In April 2014, the winner of the tender for the territory architectural and town planning concept development was determined. On December 25, 2014, the Moscow Urban Development and Land Commission (UDLC) approved the territory planning project, as well as the technical assignment for the new facilities construction. In March 2016, the construction company started the construction of the SVOBODA first residential complex on the premises of the former plant. It includes five residential buildings, 5 to 27 floors high. The first house was commissioned in the spring of 2018.
The project involves the creation of social, transport and engineering infrastructure facilities at the expense of the city budget, with the city costs to be reimbursed pro rata with the construction area. The total area intended for housing is 556 hectares, the area of housing built is about 3 million sq. m. As part of the transport infrastructure development, it is planned to build a metro station.
To be defined.
2014–2020
Currently, investors are transferring land plots to the city under the agreement, to compensate for the infrastructure construction costs.1.3 million sq. m of apartments have already been built, four preschool educational institutions, four schools and a polyclinic have been commissioned, a metro station has been opened.
The project provides the creation of a multifunctional amusement park with a total area of 280 thousand sq. m under the DreamWorks franchise. The complex will include an indoor park, a Soyuzmultfilm park, a multiplex cinema, children's themed cafes, related retail and public catering facilities, a promenade, and a parking lot. A significant part of the floodplain will be landscaped and turned into a public city park, and the Moscow River bank will be provided with a pedestrian embankment. The South River Station will be reconstructed.
over RUR 50,000 bn
2014–2020
The topography was changed, with a unique landscape created. In February 2018, the first amusement installation stage in the Island of Dreams park was started, namely, the installation of highly reliable individual foundations for each of 29 facilities. Dream Island is planned to be launched in 2019.The second construction phase includes a 410-room hotel, a children's yachting school, restaurants and shops.
The project involves the Mnevnikovskaya floodplain development, including the arrangement of the Parliamentary Center, the construction of residential buildings, a skatepark, office and transport infrastructure facilities. The total reconstruction area is 351.6 hectares, 150 hectares of which are planned to be used for construction.
To be defined
To be defined
Design start.
The project involves the construction of 78,000 sq. m of real estate, including a multifunctional concert hall, an underground parking lot for 430 cars and buses, as well as the improvement of the adjacent territories, namely, streets and bridges.
The project envisages the restoration of churches that are part of the same complex as the future park.
RUR 14 bn
2014–2017
The park opening ceremony took place in September 2017.As part of the project, the comprehensive improvement of the park area that is located in proximity to the Kremlin and Red Square has been carried out. The park is used as a venue for various events.
The project involves a major reconstruction of the Complex at Moskvoretskaya Embankment, where the Peter the Great Military Academy of Strategic Missile Troops was located. The historical buildings will be preserved and adapted to arrange a hotel, and the territory itself will be open for visitors. The action plan also includes the buildings mandatory restoration and reconstruction, as well as the integration of those with the existing city social and transport infrastructure (walking routes, an interface to the Zaryadie park).
The cost of the PPP contracts concluded in 2013-2018 is over RUR 19 bn.
To be defined
There has been an open tender for the right to conclude an agreement for the SUE REM property sale, with an obligation to carry out restoration and reconstruction works in line with the current requirements. The winner is OOO GorKapStroy-Garant, which offered the contract price of RUR 10 bn with the lot starting price of RUR 8.6 bn.
The project provides for the supply of medical equipment, its installation, training of personnel to work with equipment, subsequent maintenance, repair, purchase of spare parts and consumables. The term of the contract is 10-12 years: up to 2 years - supply, 10 years - operation. Contracts provide for the establishment of the established equipment operability (downtime no more than 9 days per quarter).
The total value of the concluded LCC is RUR 19.5 bn.
2019-2031
According to the results of tenders for the right to conclude LCC in 2019, with an initial maximum price of contracts of RUR 33.5 bn, the savings amounted to RUR 14.0 bn, that is, the average price drop was 42%.
The project involves the installation (replacement) of heat counters HC (33,578 units) and the installation of data collection and transfer devices DTTD (16, 214 units). The contractor ensures the operability of 99% of the UTE during the life cycle (fines are applied in case of violation), monitors the operability through the automated process control system. From the moment of delivery, the devices arrive at the UIAC balance sheet, which monitors the fulfillment of obligations by the contractor.
The total value of four concluded LCC is RUR 31.6 bn.
2019-2031
In 2019, four LCCs were concluded for UTE and USPD, every is for 12 years old. The tender winner became a consortium of 5 companies.