Private investments in road construction
Description of road

- Distance between the Moscow City business hub and the Moscow Ring Road
- An outbound highway with transition to the Odintsovo North Bypass Road
10,3 km
length of road
6
traffic lanes
at least 100 km/h
design speed
415 000 m2
roadway area
3
pedestrian crossings
at least 3,5 m
width of dividing strip
No traffic lights
traffic features
8,9 km
length of engineering structures
22,8 km
total length of structures
at least 40 000
vehicles per day –
throughput capacity
Railway easement area
main location
Current project status
- Concession agreement concluded

Contracts concluded for the lease of
340 land plots (68,7 ha)

Easements documented for
168 land plots (23,3 ha)

Design documentation
prepared and is undergoing
the expert evaluation procedure

Planned start of construction – 2018
Description of road

106,4 km
length of road
at least 100 km/h
design speed

No traffic lights
traffic features

Railway easement area
main location

Innovative system of barrier-free toll collection
to be introduced

Connection between highways
Moscow – St. Petersburg
and Moscow – Kazan (oncoming)


Project features
The investor finances:
RUB 45 billion
construction of a road section
RUB 5 billion
construction of barrier-free toll collection system

Entire road transferred to investor for toll operation

Road provided to investor after all sections are commissioned (2020)

Investor maintains and operates the entire road

Concession period of 49 years