Industrial Zone "Rudnevo", parcel 8 (EAD)

Brief description of the industrial area

State:
Soon to be released
Address, cadastrial number of the land plot:
77:03:0010010:3233 Moscow, PZ Rudnevo, driveway under project 42, parcel №8
Functional designation of the project:
Siting of the following facilities is possible: light industry facilities, warehousing (logistics and sorting centres); business facilities. Light industry priorities: – electronics; - pharmaceuticals (manufacture of dosage forms without preparation of API); - textiles; - china and porcelain. Note: Part of the existing SPZ of a waste incineration plant and the estimated SPZ of a Metro depot. The siting of plants with class 4 or 5 health hazard is possible in accordance with the list of SanPiN 2.2.1/2.1.1.1200-03
Functional designation of the land:
Mixed business-community and industrial development
Plot:
2.70 Ha

Transport accessibility

Availability of a railway line (passenger or freight):
Lyubertsy railway station of Kazansky and Ryazansky routes. People may get there by city buses.
Motor roads (road class, number of lanes):
The existing roadway is Kosinskoe shosse (driveway under project 598), Pokrovskaya st. (driveway under project 276), a commonly used driveway linking together Pokrovskaya st.and driveway under project 598.
Availability of the subway station:
Vykhino, Novokosino – people can get there by functional bus routes. Subway station Lukhmanovskaya is in the pipeline.

Basic economic parametres of the planned project

Square:
27,000.00
Number of floors:
4-11 + 1 underground floor
Upper height limit for buildings and structures:
55 metres
Development density:
28 000 sq m per hectare
Maximum percentage of built-up territory:
0,4

Tentative (Preliminary) cost of connections to engineering services (utility grids)

Water supply:
capacity: 450.0 cu m/day, connection fee – 12.6m rubles
Domestic sewage:
capacity: 450.0 cu m/day, connection fee – 66m rubles
Storm water runoff:
surface drainage costs are determined by the project
Heat supply:
Capacity: 12.5 Gcal/h, connection fee – 65.8m rubles
Power supply:
Capacity: 8,800 KW, connection fee – 326.3m RUB
Gas supply:
the volume and cost of works will be determined by the project based on the technical specifications of Mosgaz
Brief description of the industrial area
Transport accessibility
Economic parametres
Engineering support: current state / reserve
Engineering support: current state / reserve