Brief description of the Project: The Project of transfer hubs (hereinafter referred to as TH) is aimed at creating a convenient urban environment for comfortable and quick interchanges between different kinds of transport (metro, railway transport and automobile transport). In accordance with the resolution 413 of Moscow Government dated 06.09.2011 № 413 (including changes dated 12.10.2017), a total of 251 THs are planned to be built in the territory of Moscow, of which 150 are capital THs.

Amount of financing (million rubles): To be specified.

Terms of implementation: 2014 - 2021

Result: Development of the city transport infrastructure. The implementation of the Projects will allow to evenly distribute the load between different kinds of transport and ensure the dynamism and mobility of the city's transport system.

Current implementation status: Currently, the procedures for approving the boundaries of territorial planning projects have been completed; the economic parameters (TEPs and Feasibility studies) of the majority of THs planned for construction have been calculated. The project is in the process of finalizing both the organizational and legal implementation and financial models schemes.

Based on the results of the pre-FEED studies, in October 2017, Moscow City Government had adopted the resolution No. 413-PP dated September 6, 2011, regarding the updating of the list of transport and interchange hubs.

The results of 14 open tenders for the right to conclude a Share Purchase and Sale Agreement had been summarized.

Currently, the stage of land bids acceptance for Alma-Atinskaya TH, Novokosino TH, Profsoyuznaya TH (site 2) is completed, and by the end of 2017 open auction results will be summed up.

 

 

 

SRMR (Small Ring of the Moscow Railway)

 

Brief information about the Project:

The Project of the railway infrastructure modernization on Small Ring of the Moscow Railway (SRMR MZD) is aimed at the construction of a new passenger transportation route on its basis,  providing exits to interchange to Moscow metro stations and suburban train platforms.

The volume of financing (m Rubles): 74,800,000 Rubles.

Terms of implementation:

2014 - 2016 - construction of technology;

2016 - 2021 - commercial development.

Source of funding: Construction of the technological component to be the budget expense, commercial facilities to be funded extrabudgetary, the cost of building leasehold to be  determined based on the open tenders results.

As a result (2014 - 2017.): A technological part was created at the Moscow Central Ring (MCC), and passenger traffic has been launched at the MCC since September 2016. At present, 31 MCC stations are open, 17 interchanges to the Metro and 10 exits to interchange to the suburban trans are organized. The capacity of added infrastructure will enable about 90 million passengers use MCC services until the end of 2017.

Current status of implementation: The work on structuring the commercial real estate development Project in the framework of MCC development is continuing. The scheme of Project implementation and investors attraction is defined. In the tender held in 2016 the development company Pioneer became the open tender winner for the right to purchase of 100% stake in the authorized capital of OOO Botanichesky Sad. At the moment, the company is engaged in the construction of Botanicheskiy Sad TH at MCC. The building development concept provides for the construction of more than 44.6 thousand square meters of office space, 45.4 thousand square meters of retail space, as well as a hotel area of 51.3 thousand square meters. There are about 1 thousand parking places at these facilities.

At present, the following construction sites represent commercial interest:Vladykino, Rostokino, Novohokhlovskaya, Verkhniye Kotly, Delovoy Centr, Zorge, Likhobory transfer hubs.

 

 

Website

 

ОJSC MOSINZHPROJET

 

Amount of financing (m R): To be confirmed.

Terms of implementation: 2014 - 2021

Source of funding: The construction of the technological component is planned to be carried out at the expense of the investor, which will get the right to develop the commercial part of the Project.

Result: Development of the transport infrastructure of the city.

Current implementation status: Development and approval of the boundaries of the Projects sites for designing of planned TH is completed, the scheme of attracting extrabudgetary Project financing had been approved. The results of 13 open auctions for the right to conclude a Share Purchase and Sale agreement had been summarized: LLC TH Dmitrovskaya; LLC TH Paveletskaya, JSC T TH Park Pobedy, CJSC TH Pyatnitskoe Chausse (1 section), CJSC TH Seligerskaya; JSC TH Razkazovka, CJSC TH Technopark, CJSC TH Troparevo, LLC TH Lefortovo; LLC TH Lublino; LLC TH Khovrino; CJSC TH Khoroshevskaya, LLC TH Fonvizinskaya.

Currently, a tender has been announced for stake sale in the authorized capital of LLC TH Pyatnitskoe Chausse 3. The deadline for applications acceptance: 11.12.2017. Until the end of January, 2018, the results of the open tender will be summed up.

 

 

Moscow Metro State Unitary Enterprise

 

Amount of financing (m R): To be confirmed

Terms of implementation: 2014 - 2021

Source of funding: The construction of the technological component is planned to be carried out at the expense of the investor, which will get the right to develop the commercial part of the Project.

Result: Development of transport infrastructure, updating the system of management for different transport traffic as well as for organization of transport system traffic efficiency in Moscow.

Current status of implementation: The work on the economic and legal examination of TH development Projects is ongoing; the implementation scheme is being developed to attract extrabudgetary project financing. Based on the results of the public hearings, the technical and economic parameters of the Projects had been adjusted; plans for implementing the Projects are being developed.